LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Jack County

1429 Jacksboro 345kV

1 active project totalling 201 MW is queued to connect at 1429 Jacksboro 345kV in Jack County, Texas, according to ERCOT's October 2026 report.

Active capacity
201 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
26INR0215JackGard BESSBESS201FIS Approved04/17/20280