Counties / Texas
San Patricio County power projects
San Patricio County, Texas has 26 active power projects totalling 6,650 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 2,300 MW (35%). The largest single project is Hecate Energy Arkansas Wind (1,029 MW wind). 11 projects have signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.
Active projects
26
6.7 GW capacity
IA signed or later
11
42% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
4
since Sep 2026
Changes in San Patricio County
Withdrawn
Unconfirmed
10/01/2026
Pintail Pass BESS · BESS · San Patricio County
Missing from the latest report, not yet marked withdrawn by ERCOT. Still queued at 8249 ANGSTROM 345KV: 206 MW.
−207 MW
COD change
10/01/2026
Iron Cowboy Solar · Solar · San Patricio County
Projected COD moved 12/29/2028 → 07/10/2029. Delay #1 for this project.
+6 mo
COD change
10/01/2026
Iron Cowboy Storage · BESS · San Patricio County
Projected COD moved 12/29/2028 → 07/10/2029. Delay #1 for this project.
+6 mo
MW change
10/01/2026
256 → 257 MW
All projects
For residents and landowners
- What power projects are planned in San Patricio County?
- ERCOT's October 2026 report lists 26 active projects in San Patricio County totalling 6,650 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.