28INR0306 · BESS · San Patricio County
Iron Cowboy Storage
COD delayed 1×
Iron Cowboy Storage is a 63 MW battery storage project in San Patricio County, Texas, connecting at Bus #8920 Haisley 4A 138 kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/10/2029. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0306
- Capacity
- 63 MW
- Fuel
- BESS (BA)
- Substation
- Bus #8920 Haisley 4A 138 kV
- County
- San Patricio County
- Interconnecting entity
- Vaquero II Storage LLC
- Projected COD
- 07/10/2029
- Entered queue
- 05/16/2025
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 12/29/2028 → 07/10/2029 (+6 months)
- 08/10/2026FIS Requested → IA Signed
- 05/16/2025Entered the queue with 63 MW, projected COD 12/29/2028
- 05/16/2025Screening → FIS Requested