28INR0179 · Solar · San Patricio County

Sunburst Solar

Sunburst Solar is a 302 MW solar project in San Patricio County, Texas, connecting at KATOEN (Bus#8579). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/16/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0179
Capacity
302 MW
Fuel
Solar (PV)
Interconnecting entity
Indigo Solar, LLC
Projected COD
03/16/2029
Entered queue
10/10/2024
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/23/2024
    Screening → FIS Requested
  • 10/10/2024
    Entered the queue with 302 MW, projected COD 03/16/2029

Other projects at this substation

Sunburst BESSBESS256 MWFIS Requested