26INR0211 · Solar · San Patricio County

Titus Low Carbon Ventures Solar 1

Titus Low Carbon Ventures Solar 1 is a 338 MW solar project in San Patricio County, Texas, connecting at Tap 345kV 8249 Angstrom - 8624 Grissom. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 10/16/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0211
Capacity
338 MW
Fuel
Solar (PV)
Interconnecting entity
Vaquero Solar, LLC
Projected COD
10/16/2028
Entered queue
09/21/2023
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/26/2026
    FIS Requested → IA Signed
  • 09/21/2023
    Entered the queue with 338 MW, projected COD 10/16/2028
  • 09/21/2023
    Screening → FIS Requested

Other projects at this substation

Diamond Cowboy StorageBESS104 MWIA Signed