26INR0211 · Solar · San Patricio County
Titus Low Carbon Ventures Solar 1
Titus Low Carbon Ventures Solar 1 is a 338 MW solar project in San Patricio County, Texas, connecting at Tap 345kV 8249 Angstrom - 8624 Grissom. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 10/16/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0211
- Capacity
- 338 MW
- Fuel
- Solar (PV)
- Substation
- Tap 345kV 8249 Angstrom - 8624 Grissom
- County
- San Patricio County
- Interconnecting entity
- Vaquero Solar, LLC
- Projected COD
- 10/16/2028
- Entered queue
- 09/21/2023
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/26/2026FIS Requested → IA Signed
- 09/21/2023Entered the queue with 338 MW, projected COD 10/16/2028
- 09/21/2023Screening → FIS Requested
Other projects at this substation
| Diamond Cowboy Storage | BESS | 104 MW | IA Signed |