27INR0556 · BESS · San Patricio County
Gulf Gateway Storage One
Gulf Gateway Storage One is a 301 MW battery storage project in San Patricio County, Texas, connecting at Tap 345 kV 8249 Angstrom - 8624 Grissom. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0556
- Capacity
- 301 MW
- Fuel
- BESS (BA)
- Substation
- Tap 345 kV 8249 Angstrom - 8624 Grissom
- County
- San Patricio County
- Interconnecting entity
- Gulf Gateway Storage, LLC
- Projected COD
- 12/01/2029
- Entered queue
- 08/21/2025
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/21/2025Entered the queue with 301 MW, projected COD 12/01/2029
- 08/21/2025Screening → FIS Requested
Other projects at this substation