ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0492 · Solar · San Patricio County

Gulf Gateway Solar One

Gulf Gateway Solar One is a 301 MW solar project in San Patricio County, Texas, connecting at Tap 345 kV 8249 Angstrom - 8624 Grissom. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0492
Capacity
301 MW
Fuel
Solar (PV)
Interconnecting entity
Gulf Gateway Solar, LLC
Projected COD
12/01/2029
Entered queue
04/03/2025
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/03/2025
    Entered the queue with 301 MW, projected COD 12/01/2029
  • 04/03/2025
    Screening → FIS Requested

Other projects at this substation

Gulf Gateway Storage OneBESS301 MWFIS Requested