Substation / point of interconnection ยท San Patricio County

Bus#8956 WHITEPOINT 345KV

1 active project totalling 370 MW is queued to connect at Bus#8956 WHITEPOINT 345KV in San Patricio County, Texas, according to ERCOT's October 2026 report.

Active capacity
370 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
28INR0496Blue KiteGas370FIS Requested08/29/20300