Counties / Texas
Travis County power projects
Travis County, Texas has 8 active power projects totalling 632 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 685 MW (108%). The largest single project is Giga Texas Data Center (133 MW battery storage). 2 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
8
0.6 GW capacity
IA signed or later
2
25% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
2
since Sep 2026
Changes in Travis County
COD change
10/01/2026
Blackland Prairie 2 Energy Storage · BESS · Travis County
Projected COD moved 12/01/2027 → 12/01/2030. Delay #1 for this project.
+36 mo
COD change
10/01/2026
Blackland Prairie 3 Energy Storage · BESS · Travis County
Projected COD moved 12/01/2027 → 12/01/2030. Delay #1 for this project.
+36 mo
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Giga Texas Data Center | BESS | 133 | HORNSBY Substation POIB# 7047 | IA Signed | 12/15/2025 |
| Blackland Prairie 1 Energy Storage | BESS | 102 | 9328 Austrop 138kV | IA Signed | 12/01/2027 |
| Blackland Prairie 2 Energy Storage | BESS | 102 | 9328 Austrop 138kV | FIS Requested | 12/01/2030 |
| Blackland Prairie 3 Energy Storage | BESS | 102 | 9328 Austrop 138kV | FIS Requested | 12/01/2030 |
| AP Greenport | BESS | 100 | Austrop – Lost Pines 345 kV transmission line (Bus #7040 – 9041) | FIS Approved | 11/19/2027 |
| East Blackland Battery Storage SLF | BESS | 75 | 7337 Kimbro 138kV | FIS Requested | 05/27/2028 |
| Venture Hill Storage | BESS | 70 | 7336 Gilleland Creek 138kV | FIS Requested | 12/01/2026 |
| GIGA AUSTIN SOLAR | Solar | -53 | 7047 HORNSBY Substation 138kV | FIS Requested | 03/14/2027 |
For residents and landowners
- What power projects are planned in Travis County?
- ERCOT's October 2026 report lists 8 active projects in Travis County totalling 632 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.