25INR0266 · BESS · Travis County
East Blackland Battery Storage SLF
East Blackland Battery Storage SLF is a 75 MW battery storage project in Travis County, Texas, connecting at 7337 Kimbro 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/27/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0266
- Capacity
- 75 MW
- Fuel
- BESS (BA)
- Substation
- 7337 Kimbro 138kV
- County
- Travis County
- Interconnecting entity
- DERIVA ENERGY STORAGE, LLC
- Projected COD
- 05/27/2028
- Entered queue
- 11/22/2022
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/22/2022Entered the queue with 75 MW, projected COD 05/27/2028
- 11/22/2022Screening → FIS Requested
Other projects at this substation
No other projects at this substation.