27INR0485 · BESS · Travis County

Blackland Prairie 1 Energy Storage

Blackland Prairie 1 Energy Storage is a 102 MW battery storage project in Travis County, Texas, connecting at 9328 Austrop 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/01/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0485
Capacity
102 MW
Fuel
BESS (BA)
Interconnecting entity
Balcones Ridge Resiliency LLC
Projected COD
12/01/2027
Entered queue
02/24/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/10/2026
    FIS Requested → IA Signed
  • 02/24/2025
    Entered the queue with 102 MW, projected COD 12/01/2027
  • 02/24/2025
    Screening → FIS Requested

Other projects at this substation

Blackland Prairie 2 Energy StorageBESS102 MWFIS Requested
Blackland Prairie 3 Energy StorageBESS102 MWFIS Requested