25INR0688 · BESS · Travis County
Giga Texas Data Center
COD date passed
Giga Texas Data Center is a 133 MW battery storage project in Travis County, Texas, connecting at HORNSBY Substation POIB# 7047. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/15/2025. Its projected COD of 12/15/2025 has already passed without ERCOT approval to synchronize, so the date is likely to move.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0688
- Capacity
- 133 MW
- Fuel
- BESS (BA)
- Substation
- HORNSBY Substation POIB# 7047
- County
- Travis County
- Interconnecting entity
- Giga Texas Energy, LLC
- Projected COD
- 12/15/2025
- Entered queue
- 07/30/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/30/2025FIS Approved → IA Signed
- 03/17/2025FIS Requested → FIS Approved
- 07/30/2024Entered the queue with 133 MW, projected COD 12/15/2025
- 07/30/2024Screening → FIS Requested
Other projects at this substation
No other projects at this substation.