27INR0486 · BESS · Travis County

Blackland Prairie 2 Energy Storage

COD delayed 1×

Blackland Prairie 2 Energy Storage is a 102 MW battery storage project in Travis County, Texas, connecting at 9328 Austrop 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2030. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0486
Capacity
102 MW
Fuel
BESS (BA)
Interconnecting entity
Balcones Ridge Resiliency II LLC
Projected COD
12/01/2030
Entered queue
02/24/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 12/01/2027 → 12/01/2030 (+36 months)
  • 02/24/2025
    Entered the queue with 102 MW, projected COD 12/01/2027
  • 02/24/2025
    Screening → FIS Requested

Other projects at this substation