Taylor County power projects

Taylor County, Texas has 14 active power projects totalling 3,485 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 2,188 MW (63%). The largest single project is Key City Solar SLF (989 MW solar). 4 projects have signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.

Active projects
14
3.5 GW capacity
IA signed or later
4
29% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
0
since Sep 2026

Changes in Taylor County

No changes in the reports compared so far.

All projects

For residents and landowners

What power projects are planned in Taylor County?
ERCOT's October 2026 report lists 14 active projects in Taylor County totalling 3,485 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.