LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
17INR0053 · Wind · Taylor County

HHGT repower Horse13+CallD

HHGT repower Horse13+CallD is a 44 MW wind project in Taylor County, Texas, connecting at 7046 Kendal 345kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 03/31/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
17INR0053
Capacity
44 MW
Fuel
Wind (WT)
Interconnecting entity
Nextera
Projected COD
03/31/2027
Entered queue
06/26/2009
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/10/2021
    IA Signed → Sync Approved
  • 07/06/2017
    FIS Requested → FIS Approved
  • 10/03/2016
    Screening → FIS Requested
  • 06/26/2009
    Entered the queue with 44 MW, projected COD 03/31/2027
  • 06/26/2009
    FIS Approved → IA Signed