24INR0488 · BESS · Taylor County
Forts Trail BESS 2
Forts Trail BESS 2 is a 206 MW battery storage project in Taylor County, Texas, connecting at 11406 Central Bluff Switch 345 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/02/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0488
- Capacity
- 206 MW
- Fuel
- BESS (BA)
- Substation
- 11406 Central Bluff Switch 345 kV
- County
- Taylor County
- Interconnecting entity
- JC Central Bluff, LLC
- Projected COD
- 03/02/2029
- Entered queue
- 02/01/2023
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/01/2023Entered the queue with 206 MW, projected COD 03/02/2029
- 02/01/2023Screening → FIS Requested
Other projects at this substation
No other projects at this substation.