27INR0504 · Solar · Taylor County
Dog Star Solar II
Dog Star Solar II is a 499 MW solar project in Taylor County, Texas, connecting at Bluff Creek (Bus #60040) to Mulberry Creek (Bus #6235) 345 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0504
- Capacity
- 499 MW
- Fuel
- Solar (PV)
- County
- Taylor County
- Interconnecting entity
- Dog Star Solar LLC
- Projected COD
- 12/31/2027
- Entered queue
- 06/20/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/20/2025Entered the queue with 499 MW, projected COD 12/31/2027
- 06/20/2025Screening → FIS Requested