LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0293 · BESS · Taylor County

Dart Energy Storage A1

Withdrawn

Dart Energy Storage A1 is a 50 MW battery storage project in Taylor County, Texas, with no point of interconnection listed. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0293
Capacity
50 MW
Fuel
BESS
Substation
Not listed
Interconnecting entity
Not listed
Projected COD
n/a
Entered queue
08/13/2026
ERCOT zone
n/a
Size category
n/a

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/13/2026
    Listed as inactive

Other projects at this substation

No other projects at this substation.