26INR0618 · BESS · Taylor County
Taylor County Paul Storage
Taylor County Paul Storage is a 205 MW battery storage project in Taylor County, Texas, connecting at 6260 Abilene South Substation 138kV. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 12/30/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0618
- Capacity
- 205 MW
- Fuel
- BESS (BA)
- Substation
- 6260 Abilene South Substation 138kV
- County
- Taylor County
- Interconnecting entity
- DM-TCP, LLC
- Projected COD
- 12/30/2029
- Entered queue
- 12/05/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/09/2026FIS Requested → FIS Approved
- 12/05/2024Entered the queue with 205 MW, projected COD 12/30/2029
- 12/05/2024Screening → FIS Requested
Other projects at this substation
No other projects at this substation.