26INR0622 · Wind · Taylor County

Buffalo Gap 1 Wind Repower

Buffalo Gap 1 Wind Repower is a 120 MW wind project in Taylor County, Texas, connecting at 6216 Bluff Creek Substation 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 02/01/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0622
Capacity
120 MW
Fuel
Wind (WT)
Interconnecting entity
Buffalo Gap Wind Farm, LLC
Projected COD
02/01/2027
Entered queue
02/28/2005
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/17/2026
    FIS Requested → FIS Approved
  • 01/10/2025
    Screening → FIS Requested
  • 02/28/2005
    Entered the queue with 120 MW, projected COD 02/01/2027
  • 02/28/2005
    FIS Approved → IA Signed

Other projects at this substation

No other projects at this substation.