Scurry County power projects

Scurry County, Texas has 17 active power projects totalling 5,058 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 2,870 MW (57%). The largest single project is Spectra Solar (1,200 MW solar). 5 projects have signed an interconnection agreement or reached a later stage. 7 projects in the county are listed as withdrawn or cancelled.

Active projects
17
5.1 GW capacity
IA signed or later
5
29% of active projects
Withdrawn or cancelled
7
listed by ERCOT
Changes tracked
3
since Sep 2026

Changes in Scurry County

MW change
10/01/2026
Maldives Solar · Solar · Scurry County
Requested capacity reduced.
184 → 181 MW
Stage change
09/24/2026
Cedar Draw Solar · Solar · Scurry County
Moved from FIS Requested to FIS Approved.
FIS Approved
Stage change
09/23/2026
Cedar Draw BESS · BESS · Scurry County
Moved from FIS Requested to FIS Approved.
FIS Approved

All projects

ProjectFuelMWSubstationStageCOD
Spectra SolarSolar1,20059912 Galvani 345KVIA Signed11/16/2028
Zeus Scurry BESSBESS1,043MHOS 345 kV Substation (#59911)FIS Requested10/01/2028
Zeus Scurry SolarSolar504MHOS 345 kV Substation (#59911)FIS Requested10/01/2028
Cedar Draw SolarSolar45160011 Nebula7A 345kVFIS Approved12/31/2027
Inadale BESSBESS287Tap 345 kV TONKAWAW_5 (11048) – SCURCNTYS_5 (11318) Circuit #2FIS Requested03/02/2029
Inadale SolarSolar281Tap 345 kV TONKAWAW_5 (11048) – SCURCNTYS_5 (11318) Circuit #2FIS Approved03/02/2029
Coyote WindWind24311305 Dermott 345kVSync Approved08/28/2026
Cedar Draw BESSBESS22660011 Nebula7A 345kVFIS Approved12/31/2027
Maldives SolarSolar181Galvani 345 kV station (Bus #59912)IA Signed09/25/2028
Fluvanna Max Solar SLFSolar15311305 DERMOTT 345 kVFIS Requested09/14/2029
Hide Town Energy StorageBESS10318555 Union Switch 138 kVFIS Requested10/11/2029
Roost Energy StorageBESS102the Knapp Sub (bus# 1310) – Union Switch (bus# 18555)FIS Requested09/30/2028
Helion SolarSolar10059912 GALVANI 345FIS Requested10/22/2027
Helion BESSBESS10059912 GALVANI 345FIS Requested09/16/2027
Fluvanna Max BESS SLFBESS5211305 DERMOTT 345 kVFIS Requested09/14/2029
Brazos Wind RepowerWind221064 Sun 138kVSync Approved11/14/2025
Knapp BESSBESS10KNAPPSync Approved10/24/2026
Jade Flash StorageBESS320Not listedWithdrawnn/a
Andromeda Storage IIBESS320Not listedWithdrawnn/a
Jade Thunder StorageBESS320Not listedWithdrawnn/a
Andromeda Storage IIBBESS320Not listedWithdrawnn/a
Canyon Wind AlternativeWind312Not listedWithdrawnn/a
Maldives Solar (Oncor POI)Solar184Not listedWithdrawnn/a
Canyon BESS SLFBESS0Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Scurry County?
ERCOT's October 2026 report lists 17 active projects in Scurry County totalling 5,058 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.