LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
17INR0027b · Wind · Scurry County

Coyote Wind

Coyote Wind is a 243 MW wind project in Scurry County, Texas, connecting at 11305 Dermott 345kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 08/28/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
17INR0027b
Capacity
243 MW
Fuel
Wind (WT)
Interconnecting entity
Coyote Wind
Projected COD
08/28/2026
Entered queue
04/22/2015
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 11/25/2020
    Energization Approved → Sync Approved
  • 08/24/2020
    IA Signed → Energization Approved
  • 01/31/2020
    FIS Requested → FIS Approved
  • 08/09/2016
    FIS Approved → IA Signed
  • 06/11/2015
    Screening → FIS Requested
  • 04/22/2015
    Entered the queue with 243 MW, projected COD 08/28/2026

Other projects at this substation