ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Scurry County

MHOS 345 kV Substation (#59911)

2 active projects totalling 1,547 MW are queued to connect at MHOS 345 kV Substation (#59911) in Scurry County, Texas, according to ERCOT's October 2026 report.

Active capacity
1,547 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0535Zeus Scurry BESSBESS1,043FIS Requested10/01/20280
27INR0529Zeus Scurry SolarSolar504FIS Requested10/01/20280