21INR0532 · Wind · Scurry County
Brazos Wind Repower
Brazos Wind Repower is a 22 MW wind project in Scurry County, Texas, connecting at 1064 Sun 138kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 11/14/2025.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 21INR0532
- Capacity
- 22 MW
- Fuel
- Wind (WT)
- Substation
- 1064 Sun 138kV
- County
- Scurry County
- Interconnecting entity
- BRAZOS WIND VENTURES, LLC
- Projected COD
- 11/14/2025
- Entered queue
- 11/30/2020
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/01/2023Energization Approved → Sync Approved
- 04/25/2023FIS Approved → Energization Approved
- 04/01/2022FIS Requested → FIS Approved
- 11/30/2020Entered the queue with 22 MW, projected COD 11/14/2025
- 11/30/2020Screening → FIS Requested
Other projects at this substation
No other projects at this substation.