27INR0192 · Solar · Scurry County
Cedar Draw Solar
Cedar Draw Solar is a 451 MW solar project in Scurry County, Texas, connecting at 60011 Nebula7A 345kV. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 12/31/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0192
- Capacity
- 451 MW
- Fuel
- Solar (PV)
- Substation
- 60011 Nebula7A 345kV
- County
- Scurry County
- Interconnecting entity
- Cedar Draw Solar LLC
- Projected COD
- 12/31/2027
- Entered queue
- 03/01/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/24/2026FIS Requested → FIS Approved
- 03/01/2024Entered the queue with 451 MW, projected COD 12/31/2027
- 03/01/2024Screening → FIS Requested
Other projects at this substation
| Cedar Draw BESS | BESS | 226 MW | FIS Approved |