11305 DERMOTT 345 kV
2 active projects totalling 204 MW are queued to connect at 11305 DERMOTT 345 kV in Scurry County, Texas, according to ERCOT's October 2026 report.
Active capacity
204 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0077 | Fluvanna Max Solar SLF | Solar | 153 | FIS Requested | 09/14/2029 | 0 |
| 28INR0202 | Fluvanna Max BESS SLF | BESS | 52 | FIS Requested | 09/14/2029 | 0 |