Van Zandt County power projects
Van Zandt County, Texas has 8 active power projects totalling 986 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 714 MW (72%). The largest single project is Whiskey BESS (154 MW battery storage). 4 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
8
1.0 GW capacity
IA signed or later
4
50% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
1
since Sep 2026
Changes in Van Zandt County
COD change
10/01/2026
Amador Storage · BESS · Van Zandt County
Projected COD moved 01/21/2027 → 04/08/2027. Delay #1 for this project.
+3 mo
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Whiskey BESS | BESS | 154 | 6828 Canton Tap 138 kV | IA Signed | 07/31/2027 |
| Zorro BESS | BESS | 154 | 138 kV Ben Wheeler (Bus# 6852) | IA Signed | 08/31/2027 |
| Goldfinch Solar | Solar | 151 | Tap Connection Bus 2485 Poetry Switch to 3103 Shamburger Switch | FIS Requested | 03/31/2029 |
| Caney Creek Solar | Solar | 121 | Tap 138kV 6829 Glen Pine - 6833 Explorer | IA Signed | 06/21/2027 |
| Amador Storage | BESS | 102 | 6833 Explorer Switching Station 138kV | IA Signed | 04/08/2027 |
| Edgewood BESS 1 | BESS | 102 | Tap Edgewood 138kV bus(3181) to CANTNSW_8 (3174) | FIS Requested | 03/01/2028 |
| Edgewood BESS 2 | BESS | 102 | Tap Edgewood 138kV bus(3181) to 3174 | FIS Requested | 03/01/2028 |
| Goldfinch Storage | BESS | 100 | Tap Connection Bus 2485 Poetry Switch – 3223 Shamburger Switch | FIS Requested | 03/31/2030 |
For residents and landowners
- What power projects are planned in Van Zandt County?
- ERCOT's October 2026 report lists 8 active projects in Van Zandt County totalling 986 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.