Substation / point of interconnection ยท Van Zandt County
Tap 138kV 6829 Glen Pine - 6833 Explorer
1 active project totalling 121 MW is queued to connect at Tap 138kV 6829 Glen Pine - 6833 Explorer in Van Zandt County, Texas, according to ERCOT's October 2026 report.
Active capacity
121 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 23INR0045 | Caney Creek Solar | Solar | 121 | IA Signed | 06/21/2027 | 0 |