Substation / point of interconnection ยท Van Zandt County
138 kV Ben Wheeler (Bus# 6852)
1 active project totalling 154 MW is queued to connect at 138 kV Ben Wheeler (Bus# 6852) in Van Zandt County, Texas, according to ERCOT's October 2026 report.
Active capacity
154 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0384 | Zorro BESS | BESS | 154 | IA Signed | 08/31/2027 | 0 |