LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Van Zandt County

Tap Edgewood 138kV bus(3181) to CANTNSW_8 (3174)

1 active project totalling 102 MW is queued to connect at Tap Edgewood 138kV bus(3181) to CANTNSW_8 (3174) in Van Zandt County, Texas, according to ERCOT's October 2026 report.

Active capacity
102 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0317Edgewood BESS 1BESS102FIS Requested03/01/20280