LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0253 · Solar · Van Zandt County

Goldfinch Solar

Goldfinch Solar is a 151 MW solar project in Van Zandt County, Texas, connecting at Tap Connection Bus 2485 Poetry Switch to 3103 Shamburger Switch. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/31/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0253
Capacity
151 MW
Fuel
Solar (PV)
Interconnecting entity
BT DJ4M Solar, LLC
Projected COD
03/31/2029
Entered queue
09/15/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/15/2023
    Entered the queue with 151 MW, projected COD 03/31/2029
  • 09/15/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.