Tom Green County power projects
Tom Green County, Texas has 13 active power projects totalling 3,010 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 1,291 MW (43%). The largest single project is Moon Chapel Solar (402 MW solar). 1 project has signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
13
3.0 GW capacity
IA signed or later
1
8% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
0
since Sep 2026
Changes in Tom Green County
No changes in the reports compared so far.
All projects
For residents and landowners
- What power projects are planned in Tom Green County?
- ERCOT's October 2026 report lists 13 active projects in Tom Green County totalling 3,010 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.