25INR0853 · BESS · Tom Green County

Tango Lily BESS

Tango Lily BESS is a 201 MW battery storage project in Tom Green County, Texas, connecting at Tap 138kV 60008 TRIBUTE4A - 6442 REDCREEK4A. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/22/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0853
Capacity
201 MW
Fuel
BESS (BA)
Interconnecting entity
Lightsource Renewable Energy Development LLC
Projected COD
12/22/2029
Entered queue
01/20/2026
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 01/20/2026
    Entered the queue with 201 MW, projected COD 12/22/2029
  • 01/20/2026
    Screening → FIS Requested

Other projects at this substation

Tango Lily SolarSolar201 MWFIS Requested