Silver Sky Solar

Silver Sky Solar is a 402 MW solar project in Tom Green County, Texas, connecting at 6444 Red Creek 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/13/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0365
Capacity
402 MW
Fuel
Solar (PV)
Interconnecting entity
Lightsource Renewable Energy Development LLC
Projected COD
12/13/2029
Entered queue
08/12/2026
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/12/2026
    Entered the queue with 402 MW, projected COD 12/13/2029
  • 08/12/2026
    Screening → FIS Requested