Substation / point of interconnection ยท Tom Green County
345 kV 76009 Twin Buttes to 76090 Divide Double Circuit
1 active project totalling 180 MW is queued to connect at 345 kV 76009 Twin Buttes to 76090 Divide Double Circuit in Tom Green County, Texas, according to ERCOT's October 2026 report.
Active capacity
180 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 20INR0247 | Water Valley Wind Energy | Wind | 180 | IA Signed | 12/15/2027 | 0 |