Substation / point of interconnection ยท Tom Green County
Tap at Big Hill - Twin Buttes 345 kV line (76003 / 76009)
2 active projects totalling 326 MW are queued to connect at Tap at Big Hill - Twin Buttes 345 kV line (76003 / 76009) in Tom Green County, Texas, according to ERCOT's October 2026 report.
Active capacity
326 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0454 | Dove Creek Solar | Solar | 164 | FIS Requested | 07/01/2028 | 0 |
| 26INR0455 | Dove Creek Storage | BESS | 162 | FIS Requested | 07/01/2028 | 0 |