26INR0455 · BESS · Tom Green County
Dove Creek Storage
Dove Creek Storage is a 162 MW battery storage project in Tom Green County, Texas, connecting at Tap at Big Hill - Twin Buttes 345 kV line (76003 / 76009). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0455
- Capacity
- 162 MW
- Fuel
- BESS (BA)
- County
- Tom Green County
- Interconnecting entity
- Dove Creek Solar, LLC
- Projected COD
- 07/01/2028
- Entered queue
- 06/25/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/25/2024Entered the queue with 162 MW, projected COD 07/01/2028
- 06/25/2024Screening → FIS Requested
Other projects at this substation
| Dove Creek Solar | Solar | 164 MW | FIS Requested |