ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Dimmit County power projects

Dimmit County, Texas has 12 active power projects totalling 1,294 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 987 MW (76%). The largest single project is Desert Palm BESS (201 MW battery storage). 2 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.

Active projects
12
1.3 GW capacity
IA signed or later
2
17% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
1
since Sep 2026

Changes in Dimmit County

Stage change
09/14/2026
Wild Horse Desert Solar · Solar · Dimmit County
Moved from FIS Requested to FIS Approved.
FIS Approved

All projects

For residents and landowners

What power projects are planned in Dimmit County?
ERCOT's October 2026 report lists 12 active projects in Dimmit County totalling 1,294 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.