26INR0555 · BESS · Dimmit County

Desert Palm BESS

Desert Palm BESS is a 201 MW battery storage project in Dimmit County, Texas, connecting at 78280 Bevo Substation 138 kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0555
Capacity
201 MW
Fuel
BESS (BA)
Interconnecting entity
Desert Palm BESS, LLC
Projected COD
09/01/2028
Entered queue
08/08/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/24/2026
    FIS Requested → IA Signed
  • 08/08/2024
    Entered the queue with 201 MW, projected COD 09/01/2028
  • 08/08/2024
    Screening → FIS Requested