27INR0374 · BESS · Dimmit County
Velado Storage SLF
Velado Storage SLF is a 115 MW battery storage project in Dimmit County, Texas, connecting at Tap 138kV 78281 Dimmit - 8274 Conoco Chittam. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/14/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0374
- Capacity
- 115 MW
- Fuel
- BESS (BA)
- County
- Dimmit County
- Interconnecting entity
- Velado Solar, LLC
- Projected COD
- 09/14/2028
- Entered queue
- 11/05/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/05/2024Entered the queue with 115 MW, projected COD 09/14/2028
- 11/05/2024Screening → FIS Requested
Other projects at this substation
| Velado Solar SLF | Solar | 115 MW | FIS Requested |