25INR0133 · BESS · Dimmit County
Rose Quartz BESS
Rose Quartz BESS is a 101 MW battery storage project in Dimmit County, Texas, connecting at Tap 138kV 8283 Asherton - 8613 Bigwells. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/01/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0133
- Capacity
- 101 MW
- Fuel
- BESS (BA)
- Substation
- Tap 138kV 8283 Asherton - 8613 Bigwells
- County
- Dimmit County
- Interconnecting entity
- Rose Quartz BESS, LLC
- Projected COD
- 12/01/2026
- Entered queue
- 09/02/2022
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/28/2026FIS Approved → IA Signed
- 04/23/2025FIS Requested → FIS Approved
- 10/14/2022Screening → FIS Requested
- 09/02/2022Entered the queue with 101 MW, projected COD 12/01/2026