25INR0133 · BESS · Dimmit County

Rose Quartz BESS

Rose Quartz BESS is a 101 MW battery storage project in Dimmit County, Texas, connecting at Tap 138kV 8283 Asherton - 8613 Bigwells. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/01/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0133
Capacity
101 MW
Fuel
BESS (BA)
Interconnecting entity
Rose Quartz BESS, LLC
Projected COD
12/01/2026
Entered queue
09/02/2022
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/28/2026
    FIS Approved → IA Signed
  • 04/23/2025
    FIS Requested → FIS Approved
  • 10/14/2022
    Screening → FIS Requested
  • 09/02/2022
    Entered the queue with 101 MW, projected COD 12/01/2026

Other projects at this substation

No other projects at this substation.