LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
29INR0107 · Solar · Dimmit County

7L Solar SLF

7L Solar SLF is a 72 MW solar project in Dimmit County, Texas, connecting at Tap 69kV 5870 Brundage - 5868 Big Wells. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 11/13/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0107
Capacity
72 MW
Fuel
Solar (PV)
Interconnecting entity
7L Solar, LLC
Projected COD
11/13/2029
Entered queue
09/12/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/12/2025
    Entered the queue with 72 MW, projected COD 11/13/2029
  • 09/12/2025
    Screening → FIS Requested

Other projects at this substation

7L Storage SLFBESS0 MWFIS Requested