LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Crockett County power projects

Crockett County, Texas has 9 active power projects totalling 1,945 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 725 MW (37%). The largest single project is Midnight Sun Energy Storage (524 MW battery storage). 3 projects have signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.

Active projects
9
1.9 GW capacity
IA signed or later
3
33% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
1
since Sep 2026

Changes in Crockett County

MW change
10/01/2026
Oasis wind · Wind · Crockett County
Requested capacity increased.
300 → 350 MW

All projects

ProjectFuelMWSubstationStageCOD
Midnight Sun Energy StorageBESS5246601 Rio Pecos 138kVIA Signed06/29/2028
Gridline SolarSolar40076005 Schneeman Draw LCRAFIS Requested07/01/2029
Oasis windWind3506562 Friend Ranch Station 138kVFIS Requested07/01/2030
Big Sampson WindWind265tap 345kV 76015 Cedar Canyon - 7053 NoelkeSync Approved09/01/2026
Ranchero BESSBESS1507053 Noelke 345 kVFIS Requested04/30/2028
BLACK BEAR SOLARSolar103#6564 ILLN4A 138 KVFIS Requested06/01/2028
Blue Sky SolSolar1016562 Friends Ranch 138kVIA Signed12/31/2027
BLACK BEAR BESSBESS51#6564 ILLN4A 138kVFIS Requested06/01/2028
Blue Sky Storage SLFBESS0138 kV Friend Ranch (Bus# 6562)FIS Requested06/30/2028
Shamrock II WindWind257Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Crockett County?
ERCOT's October 2026 report lists 9 active projects in Crockett County totalling 1,945 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.