16INR0104 · Wind · Crockett County
Big Sampson Wind
Big Sampson Wind is a 265 MW wind project in Crockett County, Texas, connecting at tap 345kV 76015 Cedar Canyon - 7053 Noelke. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 09/01/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 16INR0104
- Capacity
- 265 MW
- Fuel
- Wind (WT)
- County
- Crockett County
- Interconnecting entity
- Big Sampson Wind Project, LLC
- Projected COD
- 09/01/2026
- Entered queue
- 05/11/2015
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/16/2025Energization Approved → Sync Approved
- 06/04/2025IA Signed → Energization Approved
- 10/30/2024FIS Requested → FIS Approved
- 11/08/2019FIS Approved → IA Signed
- 05/11/2015Entered the queue with 265 MW, projected COD 09/01/2026
- 05/11/2015Screening → FIS Requested