26INR0365 · Solar · Crockett County
BLACK BEAR SOLAR
BLACK BEAR SOLAR is a 103 MW solar project in Crockett County, Texas, connecting at #6564 ILLN4A 138 KV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0365
- Capacity
- 103 MW
- Fuel
- Solar (PV)
- Substation
- #6564 ILLN4A 138 KV
- County
- Crockett County
- Interconnecting entity
- ESCONDIDO DRAW RESOURCES, LLC
- Projected COD
- 06/01/2028
- Entered queue
- 12/04/2023
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/17/2024Screening → FIS Requested
- 12/04/2023Entered the queue with 103 MW, projected COD 06/01/2028
Other projects at this substation
No other projects at this substation.