1 active project totalling 524 MW is queued to connect at 6601 Rio Pecos 138kV in Crockett County, Texas, according to ERCOT's October 2026 report.

Active capacity
524 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
24INR0442Midnight Sun Energy StorageBESS524IA Signed06/29/20280