28INR0012 · Wind · Crockett County

Shamrock II Wind

Withdrawn

Shamrock II Wind is a 257 MW wind project in Crockett County, Texas, with no point of interconnection listed. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0012
Capacity
257 MW
Fuel
Wind
Substation
Not listed
Interconnecting entity
Not listed
Projected COD
n/a
Entered queue
02/07/2024
ERCOT zone
n/a
Size category
n/a

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/07/2024
    Listed as inactive

Other projects at this substation

No other projects at this substation.