LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Robertson County power projects

Robertson County, Texas has 20 active power projects totalling 3,889 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 2,598 MW (67%). The largest single project is Big Rooter East Solar (555 MW solar). 6 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.

Active projects
20
3.9 GW capacity
IA signed or later
6
30% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
1
since Sep 2026

Changes in Robertson County

COD change
10/01/2026
Tidwell Prairie II Batt · BESS · Robertson County
Projected COD moved 10/26/2026 → 12/03/2026. Delay #1 for this project.
+1 mo

All projects

ProjectFuelMWSubstationStageCOD
Big Rooter East SolarSolar55539950 TNP One Plant 345 kVIA Signed05/31/2029
BRP Mekong BESSBESS410Tap 345 kV line from Twin Oak Switch (#3400) to TPN One Plant Switchyard (#39950)FIS Requested12/01/2027
Big Rooter West SolarSolar40339950# TNTNP_ONE_3 345 KVIA Signed05/31/2028
Buffalo Prairie StorageBESS308Tap 345kV 975 Jack Creek - 3400 Twin OakFIS Requested09/30/2028
Buffalo Meadow SolarSolar251Tap Jack Creek (975) - Twin Oak (3400) 345kV lineFIS Requested09/30/2028
Bee Branch IABESS204Tap TNP ONE 39950 and Twin Oak 3400IA Signed06/01/2027
Tidwell Prairie II BattBESS204Tap 345kV 3400 Twin Oak - 39950 TNP OneIA Signed12/03/2026
Barton Branch IABESS204Tap 345kV 3400 Twin Oak - 39950 TNP OneIA Signed10/01/2026
Big Rooter West StorageBESS20139950# TNTNP_ONE_3 345 KVFIS Requested12/01/2028
Big Rooter East StorageBESS20139950 TNP One Plant 345 kVIA Signed12/31/2029
Pioneer Path Energy Storage 1BESS102Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2FIS Requested12/01/2027
Pioneer Path Energy Storage 2BESS102Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2FIS Requested12/01/2027
Pioneer Path Energy Storage 3BESS102Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2FIS Requested12/01/2027
Pioneer Path Energy Storage 4BESS102Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2FIS Requested12/01/2027
Prairie Horizon Energy Storage 1BESS102Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2FIS Requested12/01/2027
Prairie Horizon Energy Storage 2BESS102Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2FIS Requested12/01/2027
Prairie Horizon Energy Storage 3BESS102Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2FIS Requested12/01/2027
Prairie Horizon Energy Storage 4BESS102Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2FIS Requested12/01/2027
Stegall SolarSolar82Elliott (Bus #53) to Franklin (Bus #57) 69kV Transmission LineFIS Approved05/30/2027
Stegall StorageBESS50Tap connection to a new switching station on the Elliott (Bus #53) - Franklin (Bus #57) 69 kV Transmission LineFIS Approved05/30/2027

For residents and landowners

What power projects are planned in Robertson County?
ERCOT's October 2026 report lists 20 active projects in Robertson County totalling 3,889 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.