ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
22INR0503 · BESS · Robertson County

Tidwell Prairie II Batt

COD delayed 1×

Tidwell Prairie II Batt is a 204 MW battery storage project in Robertson County, Texas, connecting at Tap 345kV 3400 Twin Oak - 39950 TNP One. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/03/2026. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0503
Capacity
204 MW
Fuel
BESS (BA)
Interconnecting entity
Tidwell Prairie IIA LLC
Projected COD
12/03/2026
Entered queue
02/17/2021
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 10/26/2026 → 12/03/2026 (+1 months)
  • 06/16/2025
    FIS Requested → FIS Approved
  • 01/13/2025
    FIS Approved → IA Signed
  • 02/17/2021
    Entered the queue with 204 MW, projected COD 10/26/2026
  • 02/17/2021
    Screening → FIS Requested

Other projects at this substation

Barton Branch IABESS204 MWIA Signed