Substation / point of interconnection ยท Robertson County
39950 TNP One Plant 345 kV
2 active projects totalling 756 MW are queued to connect at 39950 TNP One Plant 345 kV in Robertson County, Texas, according to ERCOT's October 2026 report.
Active capacity
756 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0017 | Big Rooter East Solar | Solar | 555 | IA Signed | 05/31/2029 | 0 |
| 29INR0018 | Big Rooter East Storage | BESS | 201 | IA Signed | 12/31/2029 | 0 |